Project at a Glance
Project Title: Kalmia Road Culvert
Providing Agency: District Department of Transportation
Office: Infrastructure Project Management Administration (IPMA)
Status: PROGRESS
Type: New Construction
Start Date: January 17, 2012
Target End Date: September 28, 2012
Estimated Budget: Construction Budget: $1,900,000; Design: $624,000
Actual Budget: Design: $275,000
Milestones and Deliverables
Kalmia Road Culvert:
Ninety Percent Plan Submission: June 15 is the date the consultant will submit the 90% plan submission
Plan Approval: The Deisgin Plan will be approved August 17, 2012 by FHWA and DDOT.
Notice to Proceed with Construction: Fall 2012 is the date the contractor can officially begin working on replacing the culvert.