Lane Closures Planned for the Sousa Bridge Beginning Wednesday, January 30


Story at a Glance 

Beginning on Wednesday January 30, weather permitting; the District Department of Transportation (DDOT) will be conducting lane closures on the Sousa Bridge to install new overhead directional signs.

Media Contacts

 

WASHINGTON, DC — Beginning on Wednesday January 30, weather permitting; the District Department of Transportation (DDOT) will be conducting lane closures on the Sousa Bridge to install new overhead directional signs.

This activity will take a total of eight days to complete and includes installing the new direction signs, the poles affiliated with the signs and the electrical services needed to light the signs at night. Weather permitting all work should be completed by February 10, 2013.

The lane closures will take place on one side of the bridge at a time between 9:30 am and 3:30 pm each day.

A single lane will be kept open at all times while the two right lanes are closed.

Variable message boards will be in place to provide motorists with advance warning about the lane closures.